References

2012 Equipment assembly line for Airbus 320, France, MCE/Airbus                                                                                                            Planning, supply and installation of mechanical plant components at the Airbus plant in Saint Nazaire


2012 Drilling carriage, Austria, OÖ Boden- und Baustoffprüfstelle  
                                                                                                          Planning, supply, installation and commissioning of a drilling carriage for investigating the stability and the configuration of the soil.

 _______________________________________

 

2011 Gantry, Liebherr - Austria
Planning, supply and assembly of a gantry for Lenzing AG.

2011 Undercarriage Liebherr -  Romania
Planning, delivery and installation of a undercarriage for Egger Building Products GmbH

2011 Gantry, Liebherr - France
Planning, delivery and installation of a gantry for SIAT BRAUN.

2011 Segment manipulator, Austria, Siemens VAI
Segment manipulator for the CC7 continuous caster of the VA Stahl Linz.
 _______________________________________

2010 Segment manipulator, China, Siemens VAI
Segment manipulator for a continuous caster in the TISCO steel plant.
 _______________________________________

2009 Equipment assembly line for the Airbus A350, Germany, MCE / Airbus
Planning, supply and installation of mechanical plant components at the Airbus plant in Hamburg / Finkenwerder.
2009 Positioning Station for the Airbus A350, Germany, MCE / Airbus
Planning, supply and installation of mechanical plant components at the Airbus plants in Hamburg / Finkenwerder and Nordenham.

2009 Segment manipulator, China, Siemens VAI
Segment manipulator for a continuous caster at the Shougang steel plant.
2009 Bridge inspection cradle, Freudenau, Austria, MCE
Planning, supply and installation of two bridge inspection cradles for a railway bridge over the Freudenau port.  
 _______________________________________


2008 Draisine, Austria, Verbund Austrian Hydro Power AG Reisseck

Planning and supply of an electrically driven draisine for internal company use.
2008 Portal crane, Austria, Liebherr
Design, supply and installation of a mobile portal crane for the Nettingsdorf paper mill.
 _______________________________________


2007 Structure assembly line for the Airbus A320, Germany, MCE /Airbus

Planning, supply and installation of mechanical plant components at the Airbus plant in Hamburg / Finkenwerder.
 _______________________________________


2006 Segment manipulator, South Korea, VAI

Basic engineering for a segment manipulator for the Gwang Yang steel plant.
2006 Crane refurbishing, Austria, MCE
Overhaul of a 420 crane, VA Stahl Linz.
2006 Traun bridge, Bad Ischl, Austria, Habau
Mobile scaffolding for a bridge overhaul. 
2006 Enns Bridges, St. Valentin, Austria, Habau
Bridge inspection cradle for a total of three bridges. 
2006 Belt grinder, Austria, Daxecker
 _______________________________________


2005 Equipment line, Airbus Wide Body, Germany, MCE / Airbus

Planning, supply and installation of mechanical components for an assembly line.
2005 Segment manipulator, Sweden, VAI
Segment manipulator for a continuous caster at the Avesta steel plant.
 _______________________________________


2004 Hallstatt railway, Austria,

Modifications to the brakes of the funicular railway.
2004 Climatic wind tunnel, Austria, MCE / ÖBB
Planning and supply of the drive technology for the entry door.
2004 Wash box, Austria, Ziegelwerk Leitl
Planning and supply of a wash box for clay brick moulds.
2004 Bridge on the A21 motorway, St.Marx, Austria, Amro
Mobile scaffolding for a bridge overhaul. 
 _______________________________________


2003 Equipment hall, Airbus A380, Germany, MCE / Airbus

Planning, supply and installation of mechanical components at the Airbus plant Hamburg / Finkenwerder.
2003 Slip plant, Surinam, Klinger
2003 Hot plate stands, Austria, Europlatinen
2003 Mühlbachtal Bridge, Austria, Amro
Mobile scaffolding for a bridge overhaul. 
2003 Laussagraben Bridge, Austria, Amro
Mobile scaffolding for a bridge overhaul. 
2003 Almtal Bridge, Austria, Amro
Mobile scaffolding for a bridge overhaul. 
2003 Schlossbergbahn, Austria, Grazer Stadtwerke
Overhaul of the cars including the drive system.
2003 Inclined elevator, Austria, Vereinigte Bühnen Graz
 _______________________________________

2002 Roller milling device, Austria, VA-Stahl-Linz
 _______________________________________


1999 Theater an der Wien, Vienna, Vereinigte Bühnen Vienna

Drive technology for the stage systems.
1999 Drill head drive, Austria, VA-Stahl-Linz
Drill head drive for roller grinding shop. 
1999 Modifications to a bandsaw machine, Austria, Freiseder
 _______________________________________


1998 Staatsoper Vienna, Austria, Staatsoper

Winch and rope technology for lighting bridges.
1998 Donauturm Vienna, Austria, MCE
Installation of a rotating Bank Austria sign, supply of the drive technology.